Rehabilitation of the Eugene S. Pike House will be done in phases, prioritizing critical repairs that will the stabilize the building.
PRELIMINARY WORK
Roof Stabilization (Completed)
In 2025, with funding from Landmarks Illinois and donated labor from Berglund Construction, crews made essential repairs to the Pike House roof and covered it completely with heavy-duty tarps. This work seals the house against rain, snow, and animals, stabilizing the structure and helping prevent further deterioration while plans for full restoration move forward.
PHASE I – $1.5 million
Roof – Façade – Foundation
Phase I focuses on the most urgent repairs: stabilizing the house and sealing it against water, weather, and pests. We are finalizing details with Nurture Architecture and Berglund Construction.
Roof: The entire roof will be removed and replaced. Crews will restore the historic eaves and soffits (the roof overhangs and their undersides), repair the decorative metal cap, and install new gutters and downspouts.
Foundation: Berglund will check the condition of the concrete footings the house rests on. They will repair the mortar joints (tuckpointing) and waterproof the foundation walls inside and out, replacing damaged stones as needed. In the basement, some worn wood and steel beams and steel support posts will be replaced. A drainage system and sump pump will be installed around the perimeter to keep the basement dry. Mold will be removed, along with the old, unused mechanical equipment.
Façade: All exterior stonework will be repaired. The stone walls at the front entrance will be taken down to ground level and rebuilt using the original stones, with replacements only where needed. Mortar joints will be repaired throughout, and damaged stones on the chimneys will be replaced. The concrete front steps and landing will be replaced. Exterior stucco will be restored, wood trim painted, and the decorative columns cleaned, refinished, and repaired. A few windows will also be replaced to seal the building.
PHASE II – $2 million (estimated)
Windows – Interior – Grounds
Phase II completes the interior and grounds so the house can open as the Pike House Community Cultural Center. Nurture architecture firm will work with the Pike House Foundation and the Beverly Area Arts Alliance on the interior design and accessibility (ADA) plans. Work will begin by opening up the interior walls so the team can fully assess what’s needed.
Windows: All windows will be replaced with new casement windows that recreate the look of the original diamond-pane leaded-glass wood windows. Window trim will be replaced and painted as needed.
Interior: Nurture will work with the Pike House Foundation, and the Beverly Area Arts Alliance to design the interior, select materials, and prepare construction drawings. The inside will be rebuilt to serve the Cultural Center. Damaged framing and subfloors will be repaired or replaced. The house will get all-new insulation, drywall, electrical, plumbing, heating, and air conditioning. Plans include gallery space, classrooms and artist workspaces, a new kitchen, and restrooms. Possible additions are deepening the basement to create more artist workspace and building a new interior staircase down to it.
Grounds: The design team will plan the grounds to improve drainage, sloping the land so water flows away from the house. It will also add an accessible (ADA) route from the parking area to the back of the property. Work may include regrading, new retaining walls, an accessible ramp and entrance, and resetting the existing landscape blocks. New walkways and patios are planned for the back and possibly the east side, along with landscaping and native plant gardens.